IF AN ENGINE RUN-UP IS TO BE PERFORMED AT THE PARKING BAY, FOLLOW THE APPROVED ENGINE RUN-UP PROCEDURE. OTHERWISE, PERFORM IT AT THE DESIGNATED RUN-UP AREA.
BEFORE TAXI CHECKLIST COMPLETED
05 — ENGINE RUN-UP CHECKLIST
1AIRCRAFT POSITIONINTO WIND1
2BRAKES / AIRCRAFT RESTRAINTSECURE2
3ENGINE TEMPERATURECHECK3
4ENGINE RPM3,000 RPM4
5MAGNETO LEFTCHECK5
6RPM DROPMAX 300 RPM6
7MAGNETO RIGHTCHECK7
8RPM DROPMAX 300 RPM8
9MAGNETOSBOTH ON9
10ENGINE RESPONSECHECK10
11ENGINE INSTRUMENTSNORMAL11
12THROTTLEIDLE CHECK12
ENGINE RUN-UP CHECKLIST COMPLETED
MAGNETO CHECK: 3,000 RPM / MAXIMUM RPM DROP 300 RPM. OTHER RUN-UP RPM VALUES MUST BE VERIFIED AGAINST THE APPROVED PROCEDURE.
NORTHERN AVIATION ASSOC, THCHIANG MAI AIRSPORT AIRFIELD